Gautami Power Project

 Project Overview
 
IL&FS Engineering Services is a strategic investor along with GVK Group, NCC and IJM, in 464 MW (Phase-I) gas based combined cycle power plant at Peddapuram, East Godavari district in Andhra Pradesh state of India.
 
 Power Generation Process
 
The GPL power project facility is a dual fuel Combined Cycle Power Plant (CCPP) comprising two gas turbine generators and one steam turbine generator, all manufactured by Alstom with a capacity of 464 MW. A significant advantage of CCPPs is that the units can be installed in stages with short lead times and the installation of multiple generating units facilitates part load operation, thereby complying with dispatch instructions. The entire power generated would be sold to AP Transco.
 
 Cost and Timeline
 

Currently, construction is complete and the project is under testing & commissioning stage.

 
 Highlights
 
Location Andhra Pradesh
Project 464 MW Gautami Project
Type Gas based Power Project
Cost Rs. 1800 crores
Timeline Project construction complete
Benefits Augments power supply in coastal Andhra Pradesh and boosts industrial development